How to stop load test gracefully?

Question

The load test stops as soon as the test is stopped manually and doesn’t complete the iteration.
Is there a way to wait until current iteration is finished before stopping it?

Answer

Yes, now AppLoader has an option to end the load test after current iteration is finished.

This can be achieved from two locations:

1. Navigate to Test Analysis view and right click on the load test name in the tree while the test is running. You should be able to end the load test gracefully by selecting the "End Load Test Gracefully" option from context menu list. 

How to stop load test gracefully_ (115004435593)_end_gracefully_ta

2. Navigate to Real Time view and click on the End Load Test menu while the test is running. You should be able to End Load Test Gracefully by selecting that option from drop down menu list.

How to stop load test gracefully_ (115004435593)_end_gracefully_rt